Thurles Interchange N7 HQDC Completion Works

The Thurles Interchange project consisted of the following principle items;

  • Excavation ? 8,000m3
  • Ducting ? 2,125m
  • Piping/Drainage ? 1,726m
  • Petrol Interceptors and Attenuation Ditches
  • Kerbing ? 910m
  • Footpaths & Splitter Islands
  • Signage and Lining works
  • Crash Barrier
  • Fencing
  • Surfacing ? 13,976m2
  • Public Lighting Columns ? 25no.
  • Topsoiling & Landscaping
  • Traffic Management was extensive on this contract as the existing N7 which was been rerouted through the interchange, had to be kept live and in a two way system at all times.

Client

Bothar Hibernian

Client Representatives

Hyder Consulting Engineers

Date

June 2009 – May 2010

Contract Value

? 457 000

Location

N7 /R498 interchange, Nenagh County Tipperary