Scope of Works

The installation of approximately 350m of 110mm O.D. PE watermain to BS EN 12201-2:2011, SDR 17, 10 Bar, associated valves/connections, provision of new individual service connections to properties located along the route of the new mains and all required ancillary works.

  • Full certified testing and commissioning of the new watermain on completion.
  • Construction of new chambers for all associated valves and meters etc.
  • Crossing existing live services, including potential watermains, electricity and telecommunications ducts.
  • The preparation of a fully developed Traffic Management Plan for all stages of the works.

Client

Irish Water

Date

June 2016 – October 2016

Contract Value

€ 66 358

Location

Poulgorm, Co. Kerry