Cork IT Hard Landscaping Project

This project involved the construction of 2100m2 new architecturally designed, Coq de Bruyere hard landscaping in a heavily pedestrian area of CIT Campus Cork.

Scope of works included:

  • Site Clearance  2100m2
  • Earthworks  650m2 reduced formation levels.
  • Surface Water Drainage  200m of 225mm Carrier Pipe with 8 Associated Gullies.
  • Kerbing  450m of Kerbing
  • Foot Paths  235m2 100mm Concrete Footpaths
  • Paving  2100m2 of Coq de Bruyere Paving

Client

Cork Institute of Technology

Client Representives

Cork Institute of Technology

Date

November 2009 – January 2010

Contract Value

€ 75 000

Location

Cork Institute of Technology, Bishopstown, Cork

Date

May 19, 2010