Cork IT Hard Landscaping Project

This project involved the construction of 2100m2 new architecturally designed, ?Coq de Bruyere? hard landscaping in a heavily pedestrian area of CIT Campus Cork.

Scope of works included:

  • Site Clearance ? 2100m2
  • Earthworks ? 650m2 reduced formation levels.
  • Surface Water Drainage ? 200m of 225mm Carrier Pipe with 8 Associated Gullies.
  • Kerbing ? 450m of Kerbing
  • Foot Paths ? 235m2 100mm Concrete Footpaths
  • Paving ? 2100m2 of ?Coq de Bruyere? Paving

Client

Cork Institute of Technology

Client Representives

Cork Institute of Technology

Date

November 2009 – January 2010

Contract Value

? 75 000

Location

Cork Institute of Technology, Bishopstown, Cork

Date

May 19, 2010