Bandon IDA Laragh Civil Works Contract

The Bandon IDA Laragh WWTP Upgrade Works involved?the decommissioning of the existing treatment plant, construction of a pump station and construction of a rising main. The Upgrade Works comprised?2?No. contracts:?the?Civil Works Contract, consisting of site investigation and construction of the rising main, and the MEICA Works Contract, consisting of construction of a pump station and decommissioning of the existing treatment plant.??

Client

Irish Water

Date

October 2017 – February 2018

Contract Value

? 361 611