Bandon IDA Laragh Civil Works Contract

The Bandon IDA Laragh WWTP Upgrade Works involved the decommissioning of the existing treatment plant, construction of a pump station and construction of a rising main. The Upgrade Works comprised 2 No. contracts: the Civil Works Contract, consisting of site investigation and construction of the rising main, and the MEICA Works Contract, consisting of construction of a pump station and decommissioning of the existing treatment plant.

Client

Irish Water

Date

October 2017 – February 2018

Contract Value

€ 361 611

Date

January 22, 2021

20171129_161309
20171130_134849