GCL Flood Attenuation Ponds

GCL Flood Attenuation Ponds on the Nenagh to Limerick DB Road Project

MEIC was the contractor for all works carried out on the Benomate (Benonite) lined attenuation ponds, excavated and installed on the N7 HQDC. The works consisted of the following items:

  • All drainage in to and out of the ponds, including all head walls, manholes, culverts etc.
  • The excavation and lining of 18Nr Ponds (35,000m2 of lining in total)
  • Installation of petrol interceptors, handstops, penstocks, hydro brakes and attenuation ditches

Client

Bothar Hibernian

Client Representives

Bothar Hibernian & Hyder Consulting Engineers

Date

June 2009 – January 2010

Contract Value

€ 585 000

Location

N7 HQDC

Date

January 19, 2021