MEIC was the main contractor for the construction of the Carrigatogher Interchange. The works comprised of the completion of the main interchange at Carrigatogher and Nenagh, involving phased construction which included the following:
- Traffic Management Dublin to Limerick Road.
- Re-alignment and Widening of the Dublin to Limerick Road.
- Construction of the new slip roads leading to the interchange.
- Construction of on-line roundabouts at slip roads.
- Surfacing, kerbing, signage and lining works.
- Footpaths & Splitter Islands
- Drainage
- Construction of Petrol Interceptors & Attenuation Ditches
- Ducting
- Accommodation Works
- Public Lighting 30 No Columns
- Fencing
- Construction of Stone Faced Boundary Wall
- Crash Barrier Installation
- Topsoiling & Landscaping